We are getting some good work done this week. Here is the progress report:
- The septic rework is done.
- The panels are due here Mon., July 13.
- IJoists, lumber, and other supplies should be delivered early next week.
- The floors are finished.
- The slab has been trimmed, and the sill is going in today.
- The driveway has been mostly moved to accommodate the new house.
- The greenhouse is making significant progress and should be done by week’s end.
- We’ve built a holding pen for cleared brush next to the composter.
We’ve worked out a schedule for while the boys are here that includes all four of us getting to the property by 6:30 or so (thankfully, Brad has taken the task of getting them up) and working until 9:30 or 10 (while it’s still cool). Then Brad runs me home to do my “other job,” and then he and the boys come home around noon or so. After some rest, Brad and I have been going back to the property to do a little more work from about 6 until dark, weather permitting.
I can’t wait until the panels get here. Then we’ll really be moving along.